sidebar_position: 4
title: 4. Changes to a Grant
---
- Accepted grant applications can be amended at any time. However, this _necessitates a reevaluation by the committee_ and the same number of approvals as an application (according to the [levels](../Introduction/levels.md)). If your application has been accepted and, during development, you find that your project significantly deviates from the original specification, please open a new pull request that modifies the existing application. This also applies in case of significant delays.
- If your _delivery schedule_ significantly changes, please also open a pull request with an updated timeline.
- If your deliveries are significantly delayed and we cannot get a hold of you, we will terminate the grant (3 approvals required, regardless of level. If a member of the committee creates the termination PR, only 2 more approvals are required).