CPM Algorithm Implementation

Implements the Critical Path Method (CPM) algorithm:

  1. Forward pass: Calculate earliest start/finish times (ES/EF)
  2. Backward pass: Calculate latest start/finish times (LS/LF)
  3. Float calculation: slack = LS - ES
  4. Critical path: critical_path is one longest prerequisite chain in execution order; critical_ids lists every zero-float (critical) task.
  5. Batch identification: Group tasks by earliest start time
  6. Bottleneck analysis: Identify tasks that block the most work

Structs§

CpmAlgorithm
CPM Algorithm calculator

Constants§

CPM_VERSION
Version of the CPM kernel’s output semantics. Bump whenever a change alters any field of CriticalPathResult for the same input, so stored plans are recomputed on open (see plan_store). Bump also when EffortEstimator defaults change, since stored plans are recomputed with the current estimator.